A complete network rebuild around a working plant.

Manufacturing & Industrial

Quokka designed and delivered the wired and wireless network, routing and security, and guided the physical works needed to support them.

Complete programme
Under 1 year
Production cutover
2 weeks
Within budget, without surprises
On time

The constraint

A brownfield change reaches beyond a network diagram. Cabling, facility access, shutdown windows and operational dependencies shape when each part can move. The new network also needed identity and device context to inform access.

Our work

Quokka and a delivery partner designed and delivered the network, security and brownfields migration. We scoped and guided the supporting cabinets, power distribution and cabling, aligning the physical works with the network design. The client’s team and specialist contractors carried out those installations.

From facility requirements to a working network.
Physical worksScope & guide

Cabinet requirements · power distribution · fibre and copper routes

Network engineeringDesign & deliver

Wired and wireless · routing · security segregation · network access control

Operational readinessTest & hand over

Migration sequencing · operational checks · records and handover

A two-week cutover around live productionAlign facility readiness, network changes and testing with the plant’s operating windows.
Plant switches
30
Active access points
90
Certified copper links
6.25 km
Tested fibre runs
≈1.2 km
Project test records cover 153 certified copper links and nine fibre runs.

What changed

Design the whole network

Design wired and wireless connectivity, routing, security segregation and network access control as one system. Scope the supporting physical works and use the facility model to plan around the plant.

Build and migrate around production

Deploy 30 plant switches and 90 access points. Coordinate cabinet, cabling and power readiness with the client and the contractors, then complete the cutover over two weeks around agreed production windows.

Verify the operation and hand it over

Check network paths, device access, failure behaviour and coverage alongside the plant’s applications. Close defects and hand over the configuration, records and knowledge the operating team needs.

The result

Quokka and a delivery partner completed the network programme in under a year, with the cutover carried out over two weeks. We delivered on time, within budget and without surprises, with no unplanned production outages during delivery.

Physical works scoped and aligned with the network design
Wired and wireless connectivity, routing and security segregation
Network access control, operational testing and handover

Quokka and a delivery partner designed and delivered the network and migration. The client and specialist contractors carried out the physical works.

The engineering decisions.

We worked through the facility constraints, network design and migration sequence together, so the plant team could keep operating through the change.

Define boundaries around the work being done

The network design separates manufacturing, corporate users and facility services through routing domains and controlled communications. Cameras, access control, printing and guest access have different requirements from plant systems. The staged design accommodates legacy machinery and contractor access while making those boundaries explicit.

Align the physical works with the network design

The plant schedule covered 12 cabinet locations, including 11 new cabinets and one existing cabinet. Quokka scoped the requirements and guided the cabling and power arrangements. the client and the physical works contractors installed the infrastructure; we coordinated its readiness with switch deployment, wireless commissioning and the migration sequence.

Validate switch and link behaviour under failure

The acceptance plan checks Aruba VSX peer synchronisation, inter-switch links, VLAN consistency and link aggregation. It includes disabling individual links and routing interfaces, taking a switch out of service and checking the remaining path. Application access and traffic behaviour form part of those checks, alongside the switch configuration.

Check identity and wireless where people use them

The validation plan includes ClearPass authentication, critical application access and large data transfers. The team verified wireless coverage across operational and safety-critical areas, including areas without dependable mobile coverage. Test results and defects fed into commissioning and handover so the operating team received an environment checked against plant use.